SL4: DDA Flat Structure Lifts

ShuttleSky Lifts & Structures

MCD / DDA / SDMC Lift NOC & Lift Permission in Delhi

Our Team at Shuttesky are one of the Best DDA Lift Installation Company In delhi. We also Help in Getting NOC for DDA Lift Installation and Installation of lifts in DDA flats from MCD and SDMC.

According to announcement by DDA, Allottees of DDA flats in denotified areas will now no longer need to approach the housing authority for permission for installing lifts and can obtain the same from local bodies.

According to announcement by DDA, Allottees of DDA flats in denotified areas will now no longer need to approach the housing authority for permission for installing lifts and can obtain the same from local bodies.

Lift NOC Procedure

General

The request for seeking NOC for installation of lift and connecting bridge should be submitted by Proposing Applicants* after obtaining necessary consent from owner(s)/ legal representative(s) of at least 50% of the flats in that staircase (of that block) who shall be beneficiaries upon the installation of lifts in DDA flats. The consent from ground floor flat owners is desirable but not mandatory for seeking NOC by applicants. Application must be complete with all necessary documents/Affidavits and other pre-requisites for issue of NOC and lift installation in DDA flats.

Lift NOC Procedure

Whom to Apply

Allottees in all the Colonies where services stand transferred to MCD as well as colonies where services are with DDA shall apply to SE(HQ), DDA of concerned Zone. The NOC shall be issued by CE(HQ) after due verification of documents. After the issue of NOC by DDA, the applicants must get modified drawings approved from local Municipal Authority, in the areas which have been de-notified before actual execution of work for successful installation of Lift in DDA flats.

Lift NOC Procedure

Documents Required

While applying for NOC, the following documents/ indemnity bonds/affidavits are required to be submitted:

* A processing fee of Rs.5,000/-(non refundable) per lift will be charged by the DDA after verifying the check list (permission shall be granted within 45 days after submission of all complete acceptable documents). The payment can be made by DD in favor of concerned Sr.AO(CAU),DDA.

Note: Format of affidavit, undertaking and indemnity bond may be downloaded from DDA website “dda.org.in”.

The policy of lift installation in DDA flats, first notified on May 26, 2011, was subsequently modified on August 3, 2012, the urban body said.

It has additionally been referenced in the arrangement that the lift well will be developed adjoining the visually impaired divider so regular light, ventilation and development isn’t influenced and will be an autonomous structure.

To get the NOC for DDA lift installation, the lift should be installed in a manner that the stability of the existing structure is not affected and no weight is transferred on to the current structure.

We are a DDA compliant local body that helps in Installation of Lifts in DDA flats as well as getting NOC for DDA lift installation.

DDA flat residents face the daily challenge of using the staircase because there are no lifts in buildings built years ago. You can well imagine the plight of old people, small children, and patients using the staircase for going to the market, doctor visits, school and office commute. This everyday ordeal isn’t only inconvenient but physically painful and taxing.

The lack of lifts in older DDA flats constructed decades ago is now a major mobility issue for people and children living in them. What was once acceptable in the past is now cumbersome not only for DDA flat residents , but also those living in older MCD and CGHS ( Cooperative Group Housing Society) buildings as well.

Lifts Rules in Delhi – Elevator Installation

In modern urban living, lifts are no more a luxury, they are a fundamental necessity for independent and safe mobility. This need has led many residents to consider installing elevators in DDA, MCD and CGHS flats. However, they do not have the liberty to alter the structure without legal sanction.. Therefore, it is essential to understand the lift installation rules and regulations in Delhi before commencing any work. This is where our guide steps in to help you understand the correct legal process and start lift installation work in your building without hassles.

NOC/Sanction For Lift Installation in DDA/MCD/ CGHS Flats in Delhi

Residents of DDA, MCD, and CGHS flats cannot erect, re-erect or make any alterations to the existing building structure without getting the required NOC/Sanction for the installation of lifts. Any new lift installation work carried out without permission from the DDA or local authority like the MDC or SDMC will result in the construction work being halted and attract legal action under the DDA and DMC Acts of 1957.

Why Is It Needed?

Under the lift installation rules in Delhi for any CGHS, MDC and DDA structure, getting an NOC/Sanction is mandatory to confirm-

Permission can be obtained from-

Applications for NOC/ Sanction can be made by DDA/MCD/ CGHS flat residents. There are 2 types of applicants-

DDA/MCD/CGHS Flat Lift Installation Rules and Regulations in Delhi and NOC Approval

To get the NOC/Sanction for lift installation in a DDA/MCD/ CGHS building, the rules and regulations listed in the NOC/Sanction Policy must be carefully followed. Let us look at them below-

Click here here to read the full NOC Policy Document ( latest July 7th 2022) for DDA Lift Installation in Delhi.

List of Mandatory Documents to be attached with the NOC Application

Given below is a list of mandatory documents applicants must attach with their application for DDA flat lift installation in Delhi-

Drawings must show the lift in blue and the connecting bridge in red (scale at least 1:100).

Lifts Rules in Delhi- Elevator Installation

Lifts can be installed in –

Clearance Approvals During Lift Installation Construction Work

Confirms that work is being done as per approved plans.

NOC from RWA / CGHS Managing Committee if water lines, cables, etc. are shifted.

After Lift Installation For The Completion Certificate

Architects must inform DDA/MCD authorities that construction is completed as per approval.

Clearance from a Government Lift Inspector confirming the lift is safe to operate.

Especially where fire safety systems are affected.

Clearance for electrical connection and safe power supply to the lift.

Only after all above approvals are submitted.

Fees Applicable for a DDA Compliant Lift

INR 5000 fee ( Non-refundable) for application processing + development charges INR 25,000 for Colonies A and B, INR 15,000 for colonies E,G, and H, for other colonies including C and D, INR 10,000.

Please Note:

Noc Validity For DDA Flat Lift Installation In Delhi

Validity of NOC is for 5 Years

Compliance with lift rules and regulations in Delhi isn’t optional, it is essential. If you are planning to install a lift in your DDA, MCD or CGHS flat, follow the guidelines listed above to

begin the process. Since the procedure is complex and can be overwhelming for applicants, please feel free to reach out to our experienced experts for guidance, support and assistance. We will be delighted to help!

Scroll to Top